Construction has been scheduled to begin for the Wisconsin Trend Home. The date of the ground blasting is set for Monday, February 18th at 10:00 a.m at 1512 Rockridge Way, Waukesha. In addition to the ground blasting, there will be a short ceremony attended by the Mayor of Waukesha, a representative from the City of Milwaukee’s Green Team, a representative from Waukesha County, along with representatives form the Metropolitan Builder's Association. The site is located in the Rolling Ridge Subdivision, which is 1.5 miles south of I-94 on Hwy G. For more information, contact the MBA.
| Task |
Days |
State Date |
| Strip Topsoil |
1 |
2/19/08 |
| Excavate |
2 |
2/19/08 |
| Foundation |
12 |
2/22/08 |
| Set Steel |
1 |
2/27/08 |
| Basement Foundation Insulation and Waterproofing |
1 |
2/28/08 |
| Install Sewer and Water |
2 |
Done |
| Backfill/Foundation Survey |
2 |
3/07/08 |
| Fax Gas/Electric Card |
1 |
3/07/08 |
| Lumber Drop |
1 |
3/10/08 |
| Set Dumpster |
1 |
3/10/08 |
| Rough Framing |
8 |
3/11/08 |
| Deliver Windows and Doors |
1 |
3/25/08 |
| Install Windows/Doors/Exterior Trim |
4 |
3/25/08 |
| Install Electrical Panel |
1 |
3/26/08 |
| Basement Underground Plumbing |
2 |
3/27/08 |
| Install Roof |
4 |
4/04/08 |
| Interior Flatwork |
2 |
4/21/08 |
| Exterior Paint |
2 |
4/18/08 |
| Rough-in Fireplace |
1 |
4/08/08 |
| Rough-in HVAC |
2 |
4/08/08 |
| Rough-in Plumbing |
4 |
4/09/08 |
| Install Solar Panels |
5 |
4/17/08 |
| HVAC – Set Furnace and Trunks |
2 |
4/23/08 |
| Install Siding |
5 |
4/21/08 |
| Rough-in Electric |
7 |
4/15/08 |
| Low Voltage – Rough |
3 |
4/18/08 |
| Install Exterior Stone and Brick |
3 |
4/18/08 |
| Punch List and Inspections |
5 |
4/24/08 |
| Install Gas & Electric Meter |
1 |
4/25/08 |
| Insulation and Inspection |
3 |
5/12/08 |
| Install Drywall and Prime |
12 |
5/20/08 |
| Install Sun Tubes |
1 |
5/22/08 |
| Insulate Attic |
1 |
5/27/08 |
| Install Garage Door |
1 |
5/27/08 |
| Deliver Cabinets and Interior Trim |
1 |
6/09/08 |
| Install Hard Surface Flooring |
10 |
6/06/08 |
| Set Cabinets and Install Trim |
6 |
6/20/08 |
| Measure Tops |
1 |
6/23/08 |
| Install Fireplace Facing |
2 |
6/26/08 |
| Paint, Stain, and Putty |
3 |
6/30/08 |
| Install Countertops |
1 |
7/02/08 |
| Deliver Built-in Appliances |
2 |
6/30/08 |
| Finish Plumbing |
2 |
7/01/08 |
| Deliver Light Fixtures |
1 |
7/07/08 |
| Finish Electric |
5 |
7/02/08 |
| Trim HVAC |
3 |
7/09/08 |
| Fireplace Set-up |
1 |
7/09/08 |
| Install Closet Shelving |
2 |
7/07/08 |
| Install Mirrors and Shower Doors |
2 |
7/08/08 |
| Drywall Touch-ups |
2 |
7/10/08 |
| Interior and Exterior Paint Touch-ups |
2 |
7/14/08 |
| Low Voltage – Finish |
3 |
7/14/08 |
| Water Treatment |
2 |
7/14/08 |
| Deliver Loose Appliances |
1 |
7/16/08 |
| Install Carpet |
2 |
7/15/08 |
| Occupancy Inspection |
1 |
7/15/08 |
| Install Garage Door Operator |
1 |
7/16/08 |
| Install Lamp Post |
1 |
7/17/08 |
| Finish Grade / Wrap up |
2 |
7/17/08 |
| Sidewalk / Driveway |
3 |
7/17/08 |
| Cleaning |
2 |
7/17/08 |
| Repair Silt Fence |
1 |
7/18/08 |
| Energy Star Inspection |
2 |
7/21/08 |
| Pick-up Dumpster |
1 |
7/22/08 |
| Customer Orientation |
2 |
7/23/08 |
| Landscaping |
5 |
7/25/08 |
| Closing Date |
|
7/30/08 |
|