Construction Schedule

Construction Begins on the Trend Home

Construction has been scheduled to begin for the Wisconsin Trend Home. The date of the ground blasting is set for Monday, February 18th at 10:00 a.m at  1512 Rockridge Way, Waukesha. In addition to the ground blasting, there will be a short ceremony attended by the Mayor of Waukesha, a representative from the City of Milwaukee’s Green Team, a representative from Waukesha County, along with representatives form the Metropolitan Builder's Association.  The site is located in the Rolling Ridge Subdivision, which is 1.5 miles south of I-94 on Hwy G.  For more information, contact the MBA.


Job Schedule

Task Days State Date
Strip Topsoil 1 2/19/08
Excavate 2 2/19/08
Foundation 12 2/22/08
Set Steel 1 2/27/08
Basement Foundation Insulation and Waterproofing 1 2/28/08
Install Sewer and Water 2 Done
Backfill/Foundation Survey 2 3/07/08
Fax Gas/Electric Card 1 3/07/08
Lumber Drop 1 3/10/08
Set Dumpster 1 3/10/08
Rough Framing 8 3/11/08
Deliver Windows and Doors 1 3/25/08
Install Windows/Doors/Exterior Trim 4 3/25/08
Install Electrical Panel 1 3/26/08
Basement Underground Plumbing 2 3/27/08
Install Roof 4 4/04/08
Interior Flatwork 2 4/21/08
Exterior Paint 2 4/18/08
Rough-in Fireplace 1 4/08/08
Rough-in HVAC 2 4/08/08
Rough-in Plumbing 4 4/09/08
Install Solar Panels 5 4/17/08
HVAC – Set Furnace and Trunks 2 4/23/08
Install Siding 5 4/21/08
Rough-in Electric 7 4/15/08
Low Voltage – Rough 3 4/18/08
Install Exterior Stone and Brick 3 4/18/08
Punch List and Inspections 5 4/24/08
Install Gas & Electric Meter 1 4/25/08
Insulation and Inspection 3 5/12/08
Install Drywall and Prime 12 5/20/08
Install Sun Tubes 1 5/22/08
Insulate Attic 1 5/27/08
Install Garage Door 1 5/27/08
Deliver Cabinets and Interior Trim 1 6/09/08
Install Hard Surface Flooring 10 6/06/08
Set Cabinets and Install Trim 6 6/20/08
Measure Tops 1 6/23/08
Install Fireplace Facing 2 6/26/08
Paint, Stain, and Putty 3 6/30/08
Install Countertops 1 7/02/08
Deliver Built-in Appliances 2 6/30/08
Finish Plumbing 2 7/01/08
Deliver Light Fixtures 1 7/07/08
Finish Electric 5 7/02/08
Trim HVAC 3 7/09/08
Fireplace Set-up 1 7/09/08
Install Closet Shelving 2 7/07/08
Install Mirrors and Shower Doors 2 7/08/08
Drywall Touch-ups 2 7/10/08
Interior and Exterior Paint Touch-ups 2 7/14/08
Low Voltage – Finish 3 7/14/08
Water Treatment 2 7/14/08
Deliver Loose Appliances 1 7/16/08
Install Carpet 2 7/15/08
Occupancy Inspection 1 7/15/08
Install Garage Door Operator 1 7/16/08
Install Lamp Post 1 7/17/08
Finish Grade / Wrap up 2 7/17/08
Sidewalk / Driveway 3 7/17/08
Cleaning 2 7/17/08
Repair Silt Fence 1 7/18/08
Energy Star Inspection 2 7/21/08
Pick-up Dumpster 1 7/22/08
Customer Orientation 2 7/23/08
Landscaping 5 7/25/08
Closing Date   7/30/08